Description
Équipe Laurence was retained by the City of Sainte-Thérèse to carry out preventive stabilization of the slopes and a 600-metre stretch of Charron Creek. The work involved clearing, earthwork, and riprap approximately two metres thick placed directly in the streambed, topped with a layer of coarse stone to prevent scour. The scope also included the addition of five access roads, installation of municipal utilities, and full revegetation of all disturbed areas. Drawing on similar experience gained at Dominique-Juteau Creek, the team deployed methods suited to the realities of a sensitive aquatic environment.
Eco-responsable and sustainable design
Challenges
Installing an oversized 2,400 mm culvert was the project’s main technical challenge. To reach the required depth, a stepped excavation was designed, requiring an excavator assembled directly on site. To maintain a continuous flow, a temporary bypass and a permanent raising of the watercourse were necessary. Newly exposed slopes were particularly vulnerable to erosion, especially during heavy spring rains, requiring rapid intervention to stabilize the surfaces and protect the creek from sediment runoff. Finally, closing the access roads at the end of construction complicated planting operations, requiring equipment specifically designed for confined spaces.
Results
Through the careful installation of structured backfill composed of appropriate materials, the work delivered long-term stabilization of the creek banks. Abundant revegetation helped protect the slopes, promote vegetation recovery and improve the area’s landscape integration. Drainage optimization enhanced overall site performance, ensuring better water management and preservation of the aquatic environment. Together, these interventions produced a stable, functional outcome in harmony with its surroundings.